Environmental Authorisation & EIA — guide

    What is environmental authorisation and when do you need it?

    Environmental authorisation is the approval required under section 24 of the National Environmental Management Act 107 of 1998 before you may start any activity listed in Listing Notices 1, 2 or 3 of the EIA Regulations, 2014, as amended. The process is either a Basic Assessment, decided within 107 days, or a Scoping and Environmental Impact Report, decided within 300 days.

    The legal framework

    Section 24 of the National Environmental Management Act 107 of 1998 requires environmental authorisation before any listed or specified activity may commence. The current EIA Regulations, published in 2014 and amended several times since, set out the assessment procedures, and three Listing Notices identify the specific activities that trigger the requirement.

    Listing Notice 1 (GN R327) lists activities generally requiring a Basic Assessment. Listing Notice 2 (GN R325) lists larger scale or higher impact activities requiring Scoping and an Environmental Impact Report. Listing Notice 3 (GN R324) lists activities that trigger authorisation only in specified geographical areas, such as certain sensitive coastal or biodiversity areas, even at a smaller scale than Notice 1 would otherwise require.

    Basic Assessment versus Scoping and EIR

    A Basic Assessment is a single-phase process: one assessment report covering the activity, alternatives, impacts and mitigation, submitted with one round of public participation. The Regulations set a 107-day statutory decision-making period once the application is accepted, though the practical timeline including the assessment itself typically runs six to twelve months.

    Scoping and Environmental Impact Reporting is a two-phase process. The scoping phase defines the issues, alternatives and specialist studies required and is itself subject to public comment and departmental approval before the second, impact assessment phase begins. The statutory decision period is 300 days once the final EIR is accepted, and the realistic overall timeline, including both phases, is commonly twelve to twenty-four months.

    Specialist studies and public participation

    Specialist studies are commissioned based on the sensitivity of the site and the nature of the activity, and commonly include ecological, heritage, visual, traffic, noise, and where relevant, wetland, geohydrology or air quality assessments. The Regulations require specialists to be suitably qualified and to declare their independence from the applicant.

    Public participation is a statutory requirement at each phase, including notifying registered interested and affected parties, placing site notices, and running a formal comment and response process, recorded in a comments and response report submitted with the final application.

    Decisions and appeals

    Once a decision is issued, any person who submitted comments during the process, including the applicant, may appeal under section 43 of NEMA within the period prescribed by the appeal regulations, generally 20 working days from notification of the decision. An appeal suspends the authorisation until it is finalised, which can materially affect project timelines.

    Because an appeal can add several months to a project, addressing objections properly during public participation, rather than leaving them to be raised on appeal, is usually the more efficient approach.

    The cost of getting the listing wrong

    Misclassifying an activity, for example treating a Listing Notice 2 activity as though it only needed a Basic Assessment, results in a defective application that the authority can refuse outright. Where an activity is started before authorisation is obtained at all, it becomes a section 24G rectification matter with its own administrative fine exposure, rather than a standard application.

    Thresholds and indicative fees

    Environmental authorisation pathways by listing notice
    Listing noticeTypical activitiesAssessmentStatutory periodRealistic timeline
    Listing Notice 1 (GN R327)Smaller footprint activities, e.g. certain infrastructure and clearingBasic Assessment107 days6 – 12 months
    Listing Notice 2 (GN R325)Larger scale activities, e.g. bulk infrastructure, mining-related activitiesScoping and EIR300 days12 – 24 months
    Listing Notice 3 (GN R324)Area-specific activities in sensitive zonesBasic Assessment (usually)107 days6 – 14 months
    Activity started without authorisationAny listed activitySection 24G rectificationNot fixed4 – 20 months

    How the process runs

    1. 1Listed activity screeningWe identify which Listing Notice activities apply to your site and confirm the correct assessment pathway.
    2. 2Scoping (where required)For Scoping and EIR matters, we prepare the scoping report defining issues, alternatives and required specialist studies.
    3. 3Specialist studiesIndependent specialists assess the relevant impacts, sequenced to inform the impact assessment report.
    4. 4Public participationWe notify and consult registered interested and affected parties and compile the comments and response report.
    5. 5Impact assessment report and lodgementThe Basic Assessment or EIR is finalised and lodged with the competent authority.
    6. 6Decision and conditions reviewWe review the Record of Decision and conditions once issued and advise on any appeal risk.
    7. 7Appeal managementWhere an appeal is lodged by any party, we manage the section 43 appeal process to protect the authorisation.

    Continue reading

    Last reviewed: 2026-09-17

    Written and reviewed by Dynamic Legal Services (Pty) Ltd, registration 2016/074955/07. Registered with the Department of Water and Sanitation, EAPASA applicant. Offices in Faerie Glen, Pretoria and Sandown, Sandton. Telephone 087 153 6207, support@dlegal.co.za. General information on South African regulatory practice, not advice on a specific matter — the first consultation is free.